Replacement of Modular Expansion Joint on Boğaziçi Bridge

Project Details
ClientGeneral Directorate of Highways
ContractorMakyol A.Ş.
Tonnage420 ton
Completion Date2017
LocationIstanbul, Turkiye
ScopeProject
Manufacturing
Erection

Project Brief

  • Dismantling existing joint
  • Assembling reinforcement materials for new joint
  • Installation of  new modular expansion joint

Nunteknik undertook the installation of joints which were produced by Maurer AG. Before closing traffic on the bridge, reinforcement works were done, deck and approaching viaducts were prepared for new joint installation. Then two traffic lane of the bridge was closed, old joint was dismantled and new joint was installed on place of it. During these works, the bridge was divided into four phases and works were done in one phase while the traffic was flowing. By following the same steps in each phase, we completed this project within 75 days.